Data Management Monthly Progress Report 201702
  • Data Management Monthly Report
February 2017 High-level Summary The DM Team prepared for the JTM in March, continued to prepare for the arrival of the DM Project Manager in Tucson, continued supporting LSST System Engineering and Operations Planning activities, added features deblending and spectral data processing and improved performance of the LSST Software Stack and completed the technical portion of R13.0, added all-sky catalog search, image cutout display features to the Prototype DAC (PDAC), completed the installation of the Mountain - Base fiber optic cable, prepared for large-scale pre-cursor data production runs at the Archive Center, and developed a draft Service ...